Exhibit 2 · Project signal
Stargate Lighthouse (Vantage, Port Washington)
Data Center · Permitting
ISO/RTO:MISOConfidence:Medium
- Status
- Permitting
- State
- WI
- County
- Ozaukee County
- Nearest city
- Port Washington
- Utility
- We Energies (WEC)
- Developer / owner
- Vantage Data Centers; Stargate JV
- Estimated load
- 900 MW
- Estimated generation
- Not disclosed
- Reported capex (as cited)
- Not publicly itemized
- Announced
- 2025
- Expected COD
- Not confirmed
- Public summary
- A planned Vantage campus tied to the Stargate program, the largest proposed data center in Wisconsin at roughly 900 MW. Grid-supplied; utility coordinating new generation.
- Grid relevance
- A second gigawatt-class Stargate site in MISO, signaling the program is spreading beyond ERCOT into the upper Midwest.
- Last updated
- 2026-06-17
- Sources
- Wikipedia: AI data centerPulled 2026-06-17https://en.wikipedia.org/wiki/AI_data_center