Exhibit 2 · Project signal

Meta Hyperion

Data Center · Under Construction
ISO/RTO:MISOConfidence:High
Status
Under Construction
State
LA
County
Richland Parish
Nearest city
Holly Ridge / Rayville
Utility
Entergy Louisiana
Developer / owner
Meta
Estimated load
5,000 MW
Estimated generation
3,800 MW
Reported capex (as cited)
Over $10B initially; $27B+ via Blue Owl Capital partnership
Announced
2024-12
Expected COD
Phased through the late 2020s
Public summary
Meta is building the largest single-campus data-center design publicly disclosed in MISO: 5 GW at full build on ~2,250 acres in northeast Louisiana, with a ~2 GW first phase targeted by 2030. Planned floor area near 4 million square feet ranks it among the largest buildings on earth. Entergy is building ~3,800 MW of new gas generation to serve the campus. (IEEE Spectrum via Quartz, May 2026.)
Grid relevance
Entergy is adding 3.8 GW of new gas generation for one customer. The project shows a utility rebuilding its generation plan around a single hyperscale load.
Last updated
2026-06-17