Exhibit 2 · Project signal
Oncor Longshore–Drill Hole 765-kV Line
Transmission · Permitting
ISO/RTO:ERCOTConfidence:High
- Status
- Permitting
- State
- TX
- County
- Permian Basin
- Nearest city
- West Texas
- Utility
- Oncor / ERCOT
- Developer / owner
- Oncor
- Estimated load
- Not disclosed
- Estimated generation
- Not disclosed
- Reported capex (as cited)
- Multi-billion (filing)
- Announced
- 2025-12
- Expected COD
- Targeted energization December 2028
- Public summary
- Oncor filed the ~180-mile Longshore–Drill Hole 765-kV line in December 2025 — the first leg of the Permian 765-kV backbone. Targeting energization by December 2028.
- Grid relevance
- First segment of a purpose-built 765-kV Permian backbone. A leading tell for whether ERCOT can carry the load growth its large-load queue implies. Signal type: transmission.
- Last updated
- 2026-07-09
- Sources
- Utility Dive: ERCOT large load queue jumped ~300%Pulled 2026-07-09https://www.utilitydive.com/news/ercots-large-load-queue-jumped-almost-300-last-year-official/808820/