PJM
Largest U.S. market and the data-center epicenter, but a looming capacity shortfall, a queue mid-overhaul, and intense political heat over ratepayer cost-shifting make timing and cost uncertain.
Author analysis. Review against primary sources before relying on this for project decisions.
Verified facts and placeholders
Facts- Total queue MW
- 118,800 MWas of 2026-06-17
- Total queue projects
- 1,006as of 2026-06-17
- Avg interconnection wait
- 8 yearsas of 2026-06-17
- Large-load queue MW
- 55,000 MWas of 2026-06-17
- Queue status
- reform-in-progress
- Large-load posture
- Developing
- Generation queue notes
- PJM has moved to a first-ready, first-served annual cycle process. Cycle 1 closed Apr. 27, 2026 with 811 new generation projects totaling 220 GW, and PJM stated there was no remaining backlog from prior queues. The Reliability Resource Initiative selected 51 projects totaling 9,361 MW UCAP, and FERC approved a temporary Expedited Interconnection Track for up to 10 large capacity-resource requests per year.
- Large-load posture rationale
- FERC's December 2025 order forced PJM to create transparent co-location rules; PJM filed compliance Jan/Feb 2026. PJM classifies large load as 50 MW+ in forecasting. Projected 6-15 GW capacity shortfall by 2027-2030 is the core tension.
Analyst read
Editorial analysis- Tier
- Mixed
- Rationale
- Largest U.S. market and the data-center epicenter, but a looming capacity shortfall, a queue mid-overhaul, and intense political heat over ratepayer cost-shifting make timing and cost uncertain.
- What's working
- Queue is moving again under Cycle 1; 811 projects totaling 220 GW submitted into the first reformed-process intake.
- Clear FERC-mandated co-location framework gives developers a defined (if costly) path.
- What's working against
- Projected 6-15 GW capacity shortfall by 2027-2030 against surging data-center demand.
- Bipartisan governor and White House pressure to make data centers bear their own infrastructure costs raises cost risk.
- One thing to watch
- FERC's June 2026 national large-load rule (RM26-4-000), which uses PJM's co-location order as a template.
- Analyst note
- PJM is where the most data-center demand wants to land and where the most friction lives. The queue restart is real progress, but anyone planning a large load here should price in cost-allocation uncertainty and a capacity market under strain. The co-location rules are the model the rest of the country is watching.
Major announced projects in this market
Exhibit 2 · supporting- Golden-to-Mars 500kV Transmission LoopTransmission · Permitting · Ashburn / Leesburg, VAN/ACOD Targeted in service by June 1, 2028
- Meta Prometheus (New Albany, Ohio)Data Center · Under Construction · New Albany, OH1,000 MWCOD Targeted online 2026-2027; on-site ~200 MW gas generation targeted Nov 2026
- Homer City Energy CampusData Center · Under Construction · Homer City, PA4,500 MWCOD Phased from 2027
- Amazon AWS Rainier (Project Rainier)Data Center · Under Construction · New Carlisle, IN2,200 MWCOD Phased; partial operation underway
Recent reforms
Source-backed- 2025-12FERC co-location show-cause order
FERC directed PJM to create three new transmission service options for co-located large loads and revise behind-the-meter generation rules to curb cost-shifting.
Source - 2026-02Co-location compliance filings
PJM filed Jan 20 and Feb 23, 2026 compliance proposals establishing a Necessary Studies process requiring co-located generators to bear upgrade costs and adjust Capacity Interconnection Rights.
Source - 2026-06FERC approves Expedited Interconnection Track
FERC approved PJM’s temporary Expedited Interconnection Track for large, shovel-ready capacity resources. PJM expects qualifying projects to execute GIAs within 10 months and be operational within three years.
Source
Upcoming milestones
Source-backed- 2026-06Base Residual Auction 2028/2029
Next capacity auction scheduled June 2026 as PJM works to return to a normal auction schedule.
Source
Sources & last updated
Provenance- Last updated
- 2026-06-17
- Source registry
- PJM Inside Lines: Cycle 1 reformed processPulled 2026-06-17 · Supports: totalQueueMW, totalQueueProjects, generationQueueNotes, queueStatushttps://insidelines.pjm.com/over-800-new-generation-projects-seek-to-connect-under-pjms-reformed-process/
- PJM Inside Lines: Reliability Resource InitiativePulled 2026-06-17 · Supports: generationQueueNotes, whatsWorkinghttps://insidelines.pjm.com/pjm-chooses-51-generation-resource-projects-to-address-near-term-electricity-demand-growth/
- Reuters: FERC approves PJM EITPulled 2026-06-17 · Supports: recentReforms, generationQueueNoteshttps://www.reuters.com/legal/litigation/us-energy-regulator-approves-pjms-fast-tracked-power-plant-interconnection-plan-2026-06-10/
- FERC PJM co-location orderPulled 2026-06-17 · Supports: recentReforms, largeLoadPosturehttps://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid-operator-create-new-rules-embrace-innovation-and
- PowerMag FERC June deadlinePulled 2026-06-17 · Supports: recentReformshttps://www.powermag.com/ferc-sets-june-deadline-to-rewrite-large-load-grid-rules-for-ai-era-power-demand/
- White & Case PJM co-location carve-out (Wood Mackenzie 55/100 GW)Pulled 2026-06-17 · Supports: largeLoadPostureRationale, largeLoadQueueMWhttps://www.whitecase.com/insight-alert/pjm-proposes-carve-out-new-services-co-located-data-centers
- interconnection.fyi: live US ISO/utility queue dataPulled 2026-06-17 · Supports: totalQueueMW, totalQueueProjectshttps://www.interconnection.fyi