ISO-NE
Docket EL26-72. FERC found ISO-NE has no express large-load interconnection or transmission service provisions. Concern flagged as less urgent than other regions but still ordered justify-or-reform. Show-cause response due Aug 17, 2026 (or Nov 15 with abeyance).
Fastest queue timelines in the country, but a small grid, high power costs, limited land, and almost no large-load demand pipeline make it a minor data-center market for now.
Author analysis. Review against primary sources before relying on this for project decisions.
Verified facts and placeholders
Facts- Total queue MW
- 14,000 MWstale · as of 2026-06-22
- Total queue projects
- 26as of 2026-07-09
- Avg interconnection wait
- 3.7 yearsstale · as of 2026-06-22
- Large-load queue MW
- 110 MWas of 2026-07-09
- Queue status
- reform-in-progress
- Large-load posture
- Developing
- Generation queue notes
- ~14 GW proposed in the Interconnection Request Queue (Jan 2026), nearly all grid-scale wind, solar, and battery. First-ready-first-served transitional cluster study launched Oct 2025 with 26 projects (~8 GW), mostly Massachusetts battery storage. Largest is SouthCoast Wind 1 at 1,200 MW.
- Large-load posture rationale
- Large-load forecast framework debuted in the 2026 CELT Report (published May 1, 2026), built from transmission-owner surveys with proposals derated by development maturity. Current pipeline is small by national standards: only a couple hundred MW of large loads in the formal study phase, headlined by a 200 MW data center in the NEMA (Greater Boston) load zone with a timeline through 2027. New England has not seen the proposal wave hitting PJM, ERCOT, or MISO.
Analyst read
Editorial analysis- Tier
- Challenged
- Rationale
- Fastest queue timelines in the country, but a small grid, high power costs, limited land, and almost no large-load demand pipeline make it a minor data-center market for now.
- What's working
- Shortest interconnection timelines in the U.S. (~3.7 yrs).
- New first-ready-first-served cluster process with real readiness gates.
- What's working against
- Small system (~14 GW queue), high regional power prices, and constrained land limit large-load siting.
- Large-load planning is nascent; little firm framework for data-center-scale loads yet.
- One thing to watch
- Whether the new large-load forecast translates into actual data-center interconnection activity, or New England stays a secondary market.
- Analyst note
- New England is the only market of the seven writing its large-load rulebook before the wave arrives. The queue is quiet, the CELT forecast just gained a large-load line, and the FERC order forces the pen. A developer who engages the region now negotiates with a grid operator that has capacity headroom and no backlog. Watch whether the show-cause response creates a formal study track. The contrast tells the story: ISO-NE's official large-load forecast sits near 110 MW while ERCOT tracks 238.6 GW.
Major announced projects in this market
Exhibit 2 · supportingProject signal tracking is intentionally blank in this baseline edition.
Recent reforms
Source-backed- 2026-052026 CELT Report — first large-load forecast
The 2026 CELT Report (published May 1, 2026) debuted ISO-NE's first-ever large load forecast component, built from transmission-owner surveys with proposals derated by development maturity. (ISO Newswire, May 2026.)
Source - 2026-03Capacity Auction Reforms — Phase 1 accepted
FERC accepted Phase 1 of ISO-NE's Capacity Auction Reforms on March 31, 2026: auctions move from three years forward to roughly one month before delivery, starting 2028. Resources must be operational to sell capacity, ending phantom entry. Phase 2 (separate summer/winter auctions plus accreditation reform) expected at FERC by end of 2026.
Source - 2025-10First transitional cluster study
Launched first-ready-first-served cluster study of 26 interconnection requests (~8 GW): 21 battery, 3 wind, 2 solar, mostly in Massachusetts. Adds financial and site-control requirements and withdrawal penalties.
Source
Upcoming milestones
Source-backed- 2026-08-17Show-cause response due (EL26-72)
ISO-NE must justify or reform its large-load tariff by August 17, 2026 (Nov 15 with abeyance).
Source - 2026-08-06
- 2026-09-24Consumer Liaison Group — Portland, ME
CLG meets Sept 24 in Portland, Maine (storage focus). The June 2 CLG meeting in Lowell, Mass. was the region's first major public forum on data center growth.
Source - 2026-10First full cluster study window
Request window for the first full cluster study opens October 2026.
Source - 2026-12Capacity Auction Reforms — Phase 2
Phase 2 (separate summer/winter auctions plus accreditation reform) expected at FERC by the end of 2026.
Source
Sources & last updated
Provenance- Last updated
- 2026-07-09
- Primary source
- https://www.iso-ne.com/participate/applications-status-changes/interconnection-process-guide
- Source registry
- ISO-NE Resource Mix key statsPulled 2026-06-22 · Supports: totalQueueMW, generationQueueNoteshttps://www.iso-ne.com/about/key-stats/resource-mix
- Utility Dive: ISO-NE cluster studyPulled 2026-06-22 · Supports: recentReforms, upcomingMilestones, generationQueueNoteshttps://www.utilitydive.com/news/iso-new-england-launches-cluster-study-of-26-battery-wind-and-solar-projec/803333/
- ISO Newswire: large-load forecast debutPulled 2026-06-22 · Supports: largeLoadPosture, recentReformshttps://isonewswire.com/2026/05/18/iso-ne-establishes-forecast-framework-for-data-centers-other-large-loads/
- Enverus 2025 Queue Outlook (via pv-magazine)Pulled 2026-06-22 · Supports: avgInterconnectionWaitYearshttps://pv-magazine-usa.com/2025/05/09/u-s-renewables-developers-face-daunting-grid-interconnection-queues/